CLIENT WESTMINSTER CITY COUNCIL/HE SIMM DURATION 6 MONTHS
VALUE £250,000 (Trial) & £650,000
The company was appointed by the client to carry out the drilling and testing of two trial boreholes on an existing council development. The successful borehole would be later incorporated into a larger ground source energy scheme to provide approximately 500 kW of heating and cooling for the replacement residential blocks.
THE WORKS
For the trial, 2 No. 135 m
deep chalk wells were drilled using direct circulation techniques at
475 mm diameter. A permanent steel casing of 340 mm diameter was installed and
sealed into the top of the Chalk
aquifer at depth of approximately 82 m, with the remainder
of the borehole left as an open-hole section through the competent
Chalk.
Boreholes were acidised to improve the yield. A series of pumping tests were carried out as part of the trail, including step tests, constant rate tests and reinjections tests on the single pair of boreholes.
The groundwater flow from the trial boreholes was sufficient to allow the council to move forward with a full open-loop ground source energy system for the re-developed estate, with a number of additional pairs of boreholes to be installed and commissioned to meet help meet the overall energy demand in conjunction with other low-carbon technologies including air-source heat pumps. A follow on package of works was awarded for drilling and equipping six boreholes, including installation of connecting HDPE pipework and service ducts.
© Subsurface Hydro Limited, 2021